Time and Work: Important formulas and solved problems
Table of Contents
Important formulas :
If A can do a piece of work in X days and B can do the same work in Y days, then both of them working together will do the same work in \\( {xy \\over x + y} \\) Days
A, B , C while working alone can complete a work x, y, and Z days respectively then they will together complete the work in \\( { XYZ \\over XY + YZ + ZX } \\) Days
Example 1: If man A completes a piece of work in 12 days & the same work is completed by B & C in 15 days respectively. In how many days the work is completed work together?
Solution: Work per day of A , B and C \\( = {1 \\over 12} + {1 \\over 15 } + {1 \\over 20} \\)
\\( = { (5 + 4 + 3) \\over 60 } = {1 \\over 5 } \\)
Total days = 5 days (Answer)
Formula method :
They together complete the work
\\( = { XYZ \\over (XY + YZ + ZX) }\\)
\\( = {12 \\times 15 \\times 20 \\over 12 \\times 15 + 15 \\times 20 + 20 \\times 12} \\)= 5 days (answer)
Two – person A and B working together, can complete a piece of work in X days. If A alone can complete the work in Y days, then B working will complete the work in \\( {xy \\over x – y} \\)Days
Example 2 : A and B together can do a piece of work in 5 days, A alone can do it in 8 days. B alone can do the same piece of work in?
Solution:
Hence, (A + B ) = 5 days , A = 8 days
B alone can finish the work in one day
\\( = {1 \\over 5 } – {1 \\over 8 } \\)
\\( = {8 – 5 \\over 40 } \\)
B finish the whole work \\( = { 40 \\over 3 } \\) Days
\\( = 13 {1 \\over 3 } Days (answer) \\)
Formula method :
By formula ,
\\( = {xy \\over x – y } \\)
\\( = {8 \\times 5 \\over 8 – 5 } \\)
\\( = 13 { 1 \\over 3 } \\) days (Answer)
If A and B working together, can finish a piece of work in X days, B and c in days, c and A in Z days then,
– A, B and C working together will finish the job in
\\( ={ 2XYZ \\over XY + YZ + ZX } \\) Days
Example 3: A and B can complete a piece of work in 8 days 12 days B and C can do it in 8 days, A, B, and C together can complete it in?
Solution: Work done by A and B in one day \\( = {1 \\over 8} \\)
Work done by B & C in one day \\( = {1 \\over 12} \\)
Work done by C and A in 1 day \\( = {1 \\over 8} \\)
Work done by A , B and C together in 1 day
\\( = {1 \\over 2} ( {1 \\over 8} + {1 \\over 12} + {1 \\over 8} )= {1 \\over 6 } \\)
A, B and C together complete the whole job = 6 days
Formula method :
A + B + C can do finish the whole work
\\( = { 2XYZ \\over XY + YZ + ZX } \\)
\\( = { 2 \\times 8 \\times 12 \\times 8 \\over 8 \\times 12 + 12 \\times 8 + 8 \\times 8 } \\)
\\( = { 2 \\times 8 \\times 12 \\times 8 \\over 96 + 96 + 64 } \\)
= 6 days ( answer )
Work efficiency of any worker inversely proportional to the time taken by him.
i.e work efficiency \\( ╬▒ = {1 \\over Time} \\)
┬а
Example 4: A is twice as good workman as B & together they finish a piece of work in 18 days. In how many days will A alone finish the work?
Solution: A : B = 2:1
Time is taken A and B = 18 days
Work done by A and B \\( = 18 \\times 3 = 54 \\) days
A will do alone \\( = { 54 \\over 2 } = 27 \\) days
Man тАУ work – Hour – formula :
- More man can do more work
- More work means more times required to do work
- More man can do some work in less time
If M1 can do W1 work. In D1 days working H1 hr/day for Rs. R1 and M2 man can do W2 work in D2 days working H2 hr/day for Rs. R2 Then,
The formula is given as:
\\( { M1 \\times D1 \\times H1 \\over w1 \\times R1 } = { M2 \\times D2 \\times H2 \\over W2 \\times R2 } \\)
Where,
M = no. of person
D = no. Of days
H = no. Of hours
W = work
R = rate(in Rs.)
Example 5: If 10 men complete half work in 12 days when they work 8 hours per day, In how many days 18 men complete the full work when they work 6 hours \over day?
Solution: By formula
\\( { M1 \\times D1 \\times H1 \\over w1 } = { M2 \\times D2 \\times H2 \\over W2 } \\)
\\( {10 \\times 12 \\times 8 \\over {1 \\over 2}} \\) \\( = {18 \\times D2 \\times 6 \\over 1} \\)
\\(
10 \\times 12 \\times 8 \\times 2 = 18 \\times D2 \\times 6 \\)
\\( D2 = {160 \\over 9} \\) \\( = 17{7 \\over 9} \\) Days (Ans)
If a men or b women can do a piece of work in d days then x men and y women together finish the whole work :
\\( D = {a \\times b \\times d \\over xb + ya} \\)
If men or b women or c child women can do a piece of work in d days then x men, y women, and z children together finish the whole work :
\\( {D = a \\times b \\times c \\times d \\over xbc + yac + zab} \\)
Example 6 : 3 men or 4 women can do a piece of work in 43 Days. In how many days 7 men & 5 women can do The same work?
Solution: 3m or 4w = 43 days
7m + 5 w = ?
From formula :
M1 D1 = M2 D2
\\( 3 m \\times 43 = (7m + 5w) \\times D2 \\)
\\( 129 m = {7m + 15 \\over 4 m} \\times D2 \\)
\\( 129 m = {43m \\over 4} \\times D2 \\)
D2 = 12 days ( answer)
Short trick :
\\( D = {a \\times b \\times d \\over xb + ya} \\)
\\( D = {3 \\times 4 \\times 43 \\over 28 + 15} \\) = 12 days (answer)
Example 7: 1 man or 2 boys or 3 girls can do a piece of work In 88 days . In how many days one man , one boy And one girl can do the same work ?
Solution: 1m = 2b = 3g = 88 days
(1m + 1b + 1g)= ?
From formula :
M1 D1 = M2 D2
\\( 3g \\times 88 = (1m + 1b + 1g) \\times D2 \\)
\\( 3g \\times 88 = {3g + 3 \\over 2g + 1g}D2 \\)
\\( 3g \\times 88 = {6g + 3g + 2g \\over 2}D2 \\)
\\( 3g \\times 88 = {11 \\over 2 g \\times D2} \\)
D2 = 48 days (answer)
Short trick :
\\( D = {a \\times b \\times c \\times d \\over xbc + yac + zab \\)
\\( D =
{1 \\times 2 \\times 3 \\times 88 \\over 6 + 2 + 3} \\)
48 days (answer)
More Study Notes on this Topic
Ready for More?
Test your knowledge with these related materials.
ЁЯУ║ Watch & Learn
Visual explanations and related video classes for better understanding.
ЁЯОе Video Resources
The Map of Mathematics
The Map of Mathematics