Multiple Choice Question
A and B working together can do a piece of work in 6 days. B alone can do the same work in 12 days. How long (in days) will A alone take to do double the work?
Explanation:
A rate = 1/12 ⇒ Double work = 2 units ⇒ Time = 24 days.